USGS ScienceSearch

Geology topics

Abagail Rhode

Publications and source records attributed to Abagail Rhode.

3 recordsLinked to original sources

Geomorphic response of the Sandy River, Oregon, to removal of Marmot Dam

The October 2007 breaching of a temporary cofferdam constructed during removal of the 15-meter (m)-tall Marmot Dam on the Sandy River, Oregon, triggered a rapid sequence of fluvial responses as ~730,000 cubic meters (m 3 ) of sand and gravel filling the former reservoir became available to a high-gradient river. Using direct measurements of sediment transport, photogrammetry, airborne light detection and ranging (lidar) surveys, and, between transport events, repeat ground surveys of the reservoir reach and channel downstream, we monitored the erosion, transport, and deposition of this sediment in the hours, days, and months following breaching of the cofferdam. Rapid erosion of reservoir sediment led to exceptional suspended-sediment and bedload-sediment transport rates near the dam site, as well as to elevated transport rates at downstream measurement sites in the weeks and months after breaching. Measurements of sediment transport 0.4 kilometers (km) downstream of the dam site during and following breaching show a spike in the transport of fine suspended sediment within minutes after breaching, followed by high rates of suspended-load and bedload transport of sand. Significant transport of gravel bedload past the measurement site did not begin until 18 to 20 hours after breaching. For at least 7 months after breaching, bedload transport rates just below the dam site during high flows remained as much as 10 times above rates measured upstream of the dam site and farther downstream. The elevated sediment load was derived from eroded reservoir sediment, which began eroding when a meters-tall knickpoint migrated about 200 m upstream in the first hour after breaching. Rapid knickpoint migration triggered vertical incision and bank collapse in unconsolidated sand and gravel, leading to rapid channel widening. Over the following days and months, the knickpoint migrated upstream more slowly, simultaneously decreasing in height and becoming less distinct. Within 7 months, the knickpoint had migrated 2 km upstream from the dam site and became a riffle-like feature approximately 1 m high and a few tens of meters long. Knickpoint migration, vertical incision, and lateral erosion evacuated about 15 percent of the initial reservoir volume (125,000 m 3 ) within 60 hours following breaching, and by the end of the high flows in May 2008, about 50 percent of the volume had been evacuated. Large stormflows in November 2008 and January 2009 eroded another 6 percent of the original volume of impounded sediment. Little additional sediment eroded during the remainder of the second year following breaching. The rapid erosion of sediment by the modest flow that accompanied dam breaching was driven mainly by the steep hydraulic gradient associated with the abrupt change of base level and knickpoint formation and was aided by the unconsolidated and cohesionless character of the reservoir sediment. In the ensuing months, transport competence diminished as channel geometry evolved and the river gradient through the reservoir reach diminished. Changes in profile gradient in conjunction with channel coarsening and widening led to a rapid slowing of the rate of reservoir erosion. Sediment transport and deposition were strongly controlled by channel-gradient discontinuities and valley morphology downstream of the dam site. Those influences led to a strong divergence of sand and gravel transport and to deposition of a sediment wedge, as much as 4 m thick, that tapered to the preremoval channel bed 1.3 km downstream of the dam site. After 2 years, that deposit contained about 25 percent of the total volume of sediment eroded from the reservoir. The balance was distributed among pools within the Sandy River gorge, a narrow bedrock canyon extending 2 to 9 km downstream of the dam site, and along the channel farther downstream. A two-fraction sediment budget for the first year following breaching indicates that most of the gravel eroded from the reservoir reach was deposited within the sediment wedge and within the gorge, whereas eroded sand largely passed through the gorge and was broadly dispersed farther downstream. The sequence of transporting flows affected the specific trajectory of reservoir erosion and downstream sediment transport during the 2 years following breaching. However, because the overall erosion was largely a consequence of knickpoint retreat and channel widening, which in the 2 years after removal had affected most of the reservoir reach, it is unlikely that the specific sequence of flows significantly affected the overall outcome. Because the knickpoint had largely passed through the reservoir within 2 years, and the remaining reservoir sediment is mostly isolated high above armored or bedrock banks, it is unlikely that substantial additional sediment from the reservoir site will enter the system unless very large flows occur. Continued channel evolution downstream of the dam site is probable as deposits formed in the first 2 years are episodically mobilized. Below the Sandy River gorge, detection of effects related to release of reservoir sediment is challenging, especially in areas of sand deposition, because of the high background supply of sand in the river and substantial channel dynamism.

Oregon

Initial fluvial response to the removal of Oregon's Marmot Dam

A temporary, 14‐meter‐high earthen cofferdam standing in place of Marmot Dam was breached on 19 October 2007, allowing the 80‐ kilometer‐long Sandy River to flow freely from Mount Hood, Oreg., to the Columbia River for the first time in nearly 100 years. Marmot Dam is one of the largest dams in the western United States (in terms of height and volume of stored sediment) to have been removed in the past 40 years, and its removal exposed approximately 730,000 cubic meters of stored sand and gravel to erosion and transport by the newly energetic mountain river. At the time, its breach represented the greatest release of sediment from any U.S. dam removal. (The March 2008 breaching of Montana's Milltown Dam exposed about 5–10 times as much sediment to potential erosion.)

Oregon

Evolving fluvial response of the Sandy River, Oregon, following removal of Marmot Dam

The October 2007 removal of Marmot Dam on the Sandy River, Oregon, triggered a rapid sequence of fluvial responses as ~730,000 m3 of sand and gravel that filled the former reservoir were suddenly exposed to an energetic river. Using direct measurements of sediment transport, photogrammetry, and repeat surveys between transport events, we monitored the erosion, transport, and redeposition of this sediment in the hours, days, and months following breaching. Measurements of suspended load and bedload documented an initial spike in the flux of fine suspended sediment in the minutes after breaching followed by high rates of suspendedand bedload transport of sand. Significant gravel transport did not begin at a measurement site 0.4 km downstream of the dam until 18–20 hours after breaching, when bedload transport achieved rates of about 60 kg/s—rates that greatly exceeded concurrent measurements of less than 10 kg/s at sites upstream and farther downstream of the dam. Bedload transport rates just below the dam site remained 10–100 times above upstream and downstream rates through subsequent high flow events during the winter and spring of 2007 and 2008. Much of the elevated sediment load was derived from eroded reservoir sediment, which initially began eroding when a multi-meter-tall knickpoint migrated upstream 200 meters in the first hour. Rapid knickpoint migration triggered bank collapse in the unconsolidated fill, which swiftly widened the channel. Over the following days and months, the knickpoint migrated slowly upchannel, simultaneously lowering and becoming less distinct. By May 2008, a riffle-like feature approximately 1 m high, a few tens of meters long, and 2 km upstream from the breached dam persisted. Knickpoint and lateral erosion evacuated ~100,000 cubic meters of sediment from the reservoir in the first 60 hours, and by the end of high flows in May 2008 about 350,000 cubic meters (45 percent of the initial reservoir volume) had been evacuated. Large stormflows in November 2008 and January 2009 eroded another 39,000 cubic meters of sediment. Thus, within 15 months of breaching, about 55 percent of the impounded sediment (390,000 cubic meters) had been eroded. Two years after breaching, only another 10,000 m3 (~400,000 m3 total) had been eroded. About 30 percent of the eroded sediment has been redeposited in a tapered wedge of sediment that extends 2 km from the former dam site to the entrance of a confined bedrock gorge. Much of the balance of the eroded sediment is distributed along and partly fills pools within the Sandy River gorge, a narrow bedrock canyon extending 2–9 km downstream of the former dam site, and along the channel farther downstream.

Oregon